Private TN College Maximizes Cooling Efficiency with Xpress
Hassle-free retrofit dramatically reduces consumption, cuts maintenance costs and extends equipment life

Facility Bio
- Nashville, TN
- CHW plant serves over one million sqft of laboratory space and medical research facilities
- 3,600 tons cooling capacity

Situation
- Traditional Primary-Secondary hydronic system
- Low CHW ΔT, high kW/ton
- JCI Metasys building automation system, no optimization sequence

Solution
- Convert to full variable flow using Integrated Primary- Secondary® system design
- Install DPTs
- Implement tekWorx Xpress optimization solution and Energy Efficiency Dashboard
Results That Exceed Client Expectations

Financial Savings
- $84,000 in annual energy savings
- 2.5 year project payback

Energy Impact
- Over 1,4000,000 kWh saved annually
- .20 kW/ton efficiency improvement

Operational Benefits
- Improved CHW flow enabled higher building space temperatures
- Pumps running in most efficient range, reduced wear and maintenance
- Real-time data on all CHW equipment makes troubleshooting faster and less expensive