Optimized Installation AND kW/ton
Property developer chooses tekWorx optimization and a packaged plant to meet new tenant’s occupancy schedule and corporate energy goals
Facility Bio
- Columbia, MD
- Data center + Class A office space
- 3 separate buildings occupied by same tenant
Situation
- Space and cooling modifications underway to accommodate new tenant
- Limited physical space and short occupancy schedule
- Site required to comply with corporate energy mandates
Solution
- Self-contained packaged CHW plant for each building
- Variable-Primary hydronic design to save space and minimize energy costs
- tekWorx CEO® to control plant and optimize kW/ton
- Integrate each plant with BAS system, connect buildings together
Results That Exceed Client Expectations
Financial Savings
- $85,000 savings vs. portfolio
- $15,000 savings vs. target
- Savings based on actual cooling production of 3,500,000 annual ton-hours
Energy Impact
- Average portfolio efficiency: .9o kW/ton
- Site target efficiency: 70 kW/ton
- Actual site efficiency (first full year): .65 kW/ton
Operational Benefits
- Fully automated system
- Ability to remotely monitor critical values, conditions and alarms
- Equipment operation automatically adjusted to minimize total plant kW/ton under all conditions
Start saving on cooling costs.Calculate your savings instantly